Data Center Registry
Balico Data Center Campus and Gas Power Plant (withdrawn)
Chatham, Pittsylvania County County, Virginia
Balico Data Center Campus and Gas Power Plant (withdrawn) is a cancelled data center in Chatham, Virginia (Pittsylvania County County), operated by Balico. The public record puts it at 750 acres. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Cancelled
- Operator
- Balico
- Facility type
- Data center
- Location
- Chatham, Pittsylvania County County, VA
- Coordinates
- 36.8300, -79.4000 (approximate)
- Power capacity
- Not established from a public source
- Land
- 750 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Power source
- On site gas
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- April 14, 2025CancelledBalico notified the county of withdrawal on April 7, 2025 and announced it on April 14, 2025 Source: Cardinal News
Opposition and litigation at this site
Yes. Organized local opposition to Balico Data Center Campus and Gas Power Plant (withdrawn) in Chatham, Pittsylvania County County, Virginia is documented in the public record, without a lawsuit on file in the sources we track. Withdrawn after months of resident pushback and postponed votes, one day before the board's scheduled final vote.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
Withdrawn after months of resident pushback and postponed votes, one day before the board's scheduled final vote.
Power and water
The original 2,200-acre proposal included a 3,500 MW natural gas power plant. The scaled-back 12-building plan on about 750 acres included on-site power.
Notes on the record
The scaled-back plan had 12 buildings of 396,000 sq ft each near Chatham, and Balico's attorney cited almost $3.7 billion over a 10-15 year buildout. A first application was withdrawn in November 2024.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Berry Hill / Southern Virginia Megasite · Berry Hill · STACK Infrastructure11 mi · Proposed · Mixed reception
- 58 East Data Campus (Route 58 East Data Center Campus) · Ringgold · Anchorstone Advisors LLC17 mi · Permitted · Contested
- Project Flash (Summit View Business Park) · Rocky Mount · Crusoe30 mi · Cancelled · Opposed
Questions people ask about this site
Is there opposition to the Balico Data Center Campus and Gas Power Plant (withdrawn) in Chatham?
Yes. Organized local opposition to Balico Data Center Campus and Gas Power Plant (withdrawn) in Chatham, Pittsylvania County County, Virginia is documented in the public record, without a lawsuit on file in the sources we track. Withdrawn after months of resident pushback and postponed votes, one day before the board's scheduled final vote.
Has anyone filed a lawsuit over the Balico Data Center Campus and Gas Power Plant (withdrawn)?
No lawsuit over Balico Data Center Campus and Gas Power Plant (withdrawn) appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Balico Data Center Campus and Gas Power Plant (withdrawn) use?
No water withdrawal figure for Balico Data Center Campus and Gas Power Plant (withdrawn) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Balico Data Center Campus and Gas Power Plant (withdrawn), and how big is it?
Balico is the operator on record. No capacity figure is on record for this site. The site is recorded at 750 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Balico Data Center Campus and Gas Power Plant (withdrawn)," updated November 4, 2026, https://suedatacenters.org/data-centers/balico-pittsylvania-data-center-campus-va.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/balico-pittsylvania-data-center-campus-va, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Balico withdraws data center proposal for Pittsylvania after months of resident pushback and vote postponements · Cardinal News · retrieved November 4, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us