Data Center Registry
Berry Hill / Southern Virginia Megasite
Berry Hill, Pittsylvania County, Virginia · All 21 STACK Infrastructure sites
Berry Hill / Southern Virginia Megasite is a proposed data center in Berry Hill, Virginia (Pittsylvania County), operated by STACK Infrastructure. The public record puts it at announced March 2026, 2,990 acres, a reported $73 billion investment. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- STACK Infrastructure
- Facility type
- Data center
- Location
- Berry Hill, Pittsylvania County, VA
- Coordinates
- 36.6800, -79.3500 (approximate)
- Power capacity
- Not established from a public source
- Land
- 2,990 acres
- Investment
- $73 billion
- Announced
- March 2026
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- 7 million gallons a day, reported
- Jobs
- 2,050 permanent
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 30, 2026ProposedSTACK confirmed moving forward. Source: Cardinal News
Opposition and litigation at this site
Partly. Both documented support and documented opposition to Berry Hill / Southern Virginia Megasite in Berry Hill, Pittsylvania County, Virginia appear in the record, with no clear majority position. The Pittsylvania County Board of Supervisors passed a resolution supporting the project, and Regional Industrial Facility Authority chair Vic Ingram publicly championed it, calling the investment historic.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
The Pittsylvania County Board of Supervisors passed a resolution supporting the project, and Regional Industrial Facility Authority chair Vic Ingram publicly championed it, calling the investment historic. Erin Hall, a resident living four miles from the megasite, spoke against the project during public comment, questioning water and power safeguards and saying county meetings had been kept 'hush-hush.'
Power and water
Performance agreement references 7 million gallons per day of water capacity allocated from the Dan River for the megasite buildout.
Notes on the record
Performance agreement caps investment at up to $73.5B over 30 years (2,050 jobs); parallel reporting cites a ~$100B project scope. ~2,990 acres of the Southern Virginia Megasite; land deal ~$737.8M. investmentUsd reflects the conservative $73B figure from the March 2026 draft performance agreement (2,050 jobs, 30-year span, not yet signed); a May 2026 'final document' revised it upward to $100B / 2,500 jobs.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- 58 East Data Campus (Route 58 East Data Center Campus) · Ringgold · Anchorstone Advisors LLC6 mi · Permitted · Contested
- Microsoft Person County Mega Park · Roxboro · Microsoft28 mi · Permitted · Contested
Questions people ask about this site
Is there opposition to the Berry Hill / Southern Virginia Megasite data center in Berry Hill?
Partly. Both documented support and documented opposition to Berry Hill / Southern Virginia Megasite in Berry Hill, Pittsylvania County, Virginia appear in the record, with no clear majority position. The Pittsylvania County Board of Supervisors passed a resolution supporting the project, and Regional Industrial Facility Authority chair Vic Ingram publicly championed it, calling the investment historic.
Has anyone filed a lawsuit over the Berry Hill / Southern Virginia Megasite data center?
No lawsuit over Berry Hill / Southern Virginia Megasite appears in the record we track as of August 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Berry Hill / Southern Virginia Megasite use?
7 million gallons a day is the reported figure on record. Performance agreement references 7 million gallons per day of water capacity allocated from the Dan River for the megasite buildout.
Who operates Berry Hill / Southern Virginia Megasite, and how big is it?
STACK Infrastructure is the operator on record. We hold 21 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 2990 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Berry Hill / Southern Virginia Megasite," updated August 26, 2026, https://suedatacenters.org/data-centers/stack-berry-hill-va.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/stack-berry-hill-va, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.STACK commits $73.5bn investment into data center campus in Berry Hill, Virginia · Data Center Dynamics · retrieved July 17, 2026
- 2.STACK Infrastructure says it's moving forward with AI data center in Pittsylvania · Cardinal News · retrieved July 17, 2026
- 3.Cardinal News · retrieved July 25, 2026
- 4.Pittsylvania supervisors back $100B Berry Hill Data Center project · WSET (ABC13) · retrieved August 19, 2026
- 5.Local leaders approve $100B AI data campus in Pittsylvania County amid citizen concerns · WSET (ABC13) · retrieved August 19, 2026
- 6.$100B data center project proposed at Berry Hill megasite advances · Virginia Business · retrieved August 26, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us