Berry Hill, Pittsylvania County, Virginia · All 23 STACK Infrastructure sites

ProposedMixed receptionAI confirmedRecord updated October 28, 2026

Berry Hill / Southern Virginia Megasite is a proposed data center in Berry Hill, Virginia (Pittsylvania County), operated by STACK Infrastructure. The public record puts it at announced March 2026, 2,990 acres, a reported $73.5 billion investment. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
STACK Infrastructure
Facility type
Data center, AI use confirmed
Location
Berry Hill, Pittsylvania County, VA
Coordinates
36.6800, -79.3500 (approximate)
Power capacity
Not established from a public source
Land
2,990 acres
Investment
$73.5 billion
Announced
March 2026
Utility
Appalachian Power
Power source
Grid
Cooling
Not established from a public source
Water use
7 million gallons a day, reported
Jobs
2,050 permanent
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. June 30, 2026
    Proposed
    STACK confirmed moving forward. Source: Cardinal News

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Berry Hill / Southern Virginia Megasite in Berry Hill, Pittsylvania County, Virginia appear in the record, with no clear majority position. The Pittsylvania County Board of Supervisors passed a resolution supporting the project, and Regional Industrial Facility Authority chair Vic Ingram publicly championed it, calling the investment historic.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

The Pittsylvania County Board of Supervisors passed a resolution supporting the project, and Regional Industrial Facility Authority chair Vic Ingram publicly championed it, calling the investment historic. Erin Hall, a resident living four miles from the megasite, spoke against the project during public comment, questioning water and power safeguards and saying county meetings had been kept 'hush-hush.'

Source: WSET (ABC13)

Power and water

Initial power allocation of ~299 MW is required by end of 2028. STACK funds APCo transmission and generation upgrades and holds contingency rights tied to APCo confirming delivery.

Performance agreement references 7 million gallons per day of water capacity allocated from the Dan River for the megasite buildout.

Notes on the record

Performance agreement sets a minimum investment of at least $73.5B over 30 years (at least 2,050 jobs); parallel reporting cites a ~$100B project scope. ~2,990 acres of the Southern Virginia Megasite; land deal ~$737.8M. The recorded investment figure is the agreement's minimum, at least $73.5 billion (Virginia Business, May 2026). The March 2026 draft agreement carried $73 billion and 2,050 jobs over 30 years (Cardinal News); Virginia Business puts the company's planned investment at about $100 billion over three decades, and Cardinal News describes the final document as outlining $100 billion and 2,500 jobs. The $100 billion figure is a planned total and is not recorded.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Berry Hill / Southern Virginia Megasite?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Berry Hill / Southern Virginia Megasite data center in Berry Hill?

Partly. Both documented support and documented opposition to Berry Hill / Southern Virginia Megasite in Berry Hill, Pittsylvania County, Virginia appear in the record, with no clear majority position. The Pittsylvania County Board of Supervisors passed a resolution supporting the project, and Regional Industrial Facility Authority chair Vic Ingram publicly championed it, calling the investment historic.

Has anyone filed a lawsuit over the Berry Hill / Southern Virginia Megasite data center?

No lawsuit over Berry Hill / Southern Virginia Megasite appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Berry Hill / Southern Virginia Megasite use?

7 million gallons a day is the reported figure on record. Performance agreement references 7 million gallons per day of water capacity allocated from the Dan River for the megasite buildout.

Who operates Berry Hill / Southern Virginia Megasite, and how big is it?

STACK Infrastructure is the operator on record. We hold 23 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 2990 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Berry Hill / Southern Virginia Megasite," updated October 28, 2026, https://suedatacenters.org/data-centers/stack-berry-hill-va.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/stack-berry-hill-va, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.STACK commits $73.5bn investment into data center campus in Berry Hill, Virginia · Data Center Dynamics · retrieved July 17, 2026
  2. 2.STACK Infrastructure says it's moving forward with AI data center in Pittsylvania · Cardinal News · retrieved July 17, 2026
  3. 3.Cardinal News · retrieved July 25, 2026
  4. 4.Pittsylvania supervisors back $100B Berry Hill Data Center project · WSET (ABC13) · retrieved August 19, 2026
  5. 5.Local leaders approve $100B AI data campus in Pittsylvania County amid citizen concerns · WSET (ABC13) · retrieved August 19, 2026
  6. 6.$100B data center project proposed at Berry Hill megasite advances · Virginia Business · retrieved August 26, 2026
  7. 7.Berry Hill $100B data center performance agreement unanimously approved by officials · Construction Review Online · retrieved October 14, 2026
  8. 8.Southside Virginia advances historic $100B Berry Hill data center campus despite resident pushback · Construction Review Online · retrieved October 14, 2026
  9. 9.A data center project in Pittsylvania was approved Monday with higher investment and jobs than previously announced · Cardinal News · retrieved October 14, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us