Sue Data Centers

Data Center Registry

Microsoft La Porte Data Center

La Porte, La Porte County, Indiana · All 45 Microsoft sites · Every Microsoft case on our tracker

Under constructionNo reception on recordAI mixed useRecord updated July 24, 2026

Microsoft La Porte Data Center is a data center under construction in La Porte, Indiana (La Porte County), operated by Microsoft. The public record puts it at announced June 2024, 489 acres, a reported $1 billion investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Microsoft
Facility type
Data center, AI use mixed
Location
La Porte, La Porte County, IN
Coordinates
41.5950, -86.7350
Power capacity
Not established from a public source
Land
489 acres
Investment
$1 billion
Announced
June 2024
Utility
NIPSCO
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
200 permanent
Public subsidy
35-year data center sales tax credit (IEDC), extendable to 45 years per additional $1B invested within first 15 years, Indiana, 2024
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. March 2026
    Under construction
    Site preparation began March 2026; Buildings 1-3 under construction through end of 2027; full completion expected 2029 Source: Data Center Dynamics
  2. 2025
    Permitted
    Entitlement (permitting) phase completed; expanded plan to 17 buildings filed Source: Data Center Dynamics
  3. June 2024
    Proposed
    Governor Holcomb announces $1B Microsoft data center at Radius Industrial Park, La Porte; announced June 4, 2024; Indiana's fourth major data center announcement of 2024 Source: City of La Porte, IN

Opposition and litigation at this site

Nothing on record as of July 24, 2026. No lawsuit, organized opposition, or contested hearing over Microsoft La Porte Data Center in La Porte, La Porte County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Public money on the record

ProgramAmountGranted byYear
35-year data center sales tax credit (IEDC), extendable to 45 years per additional $1B invested within first 15 yearsNot establishedIndiana2024

Notes on the record

Radius Industrial Park, La Porte IN (La Porte County, NW Indiana). Initial plan 245,000 sq ft on 489 acres; expanded to 17 buildings with adjacent rezoning sought. First-phase six data centers plus substation. Microsoft stated 'Community-First AI Infrastructure' principles. Coordinates are approximate Radius Industrial Park area. Announcement date corrected from 2024-09 to 2024-06 per IEDC press release dated June 4, 2024.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • How the community has received it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Microsoft La Porte Data Center in La Porte?

Nothing on record as of July 24, 2026. No lawsuit, organized opposition, or contested hearing over Microsoft La Porte Data Center in La Porte, La Porte County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Microsoft La Porte Data Center?

No lawsuit over Microsoft La Porte Data Center appears in the record we track as of July 24, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Microsoft La Porte Data Center use?

No water withdrawal figure for Microsoft La Porte Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Microsoft La Porte Data Center, and how big is it?

Microsoft is the operator on record. We hold 45 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 489 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Microsoft La Porte Data Center," updated July 24, 2026, https://suedatacenters.org/data-centers/microsoft-laporte-in.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/microsoft-laporte-in, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Gov. Holcomb announces plans for new $1B Microsoft Data Center in Northwest Indiana · City of La Porte, IN · retrieved July 6, 2026
  2. 2.Microsoft expands plans for La Porte, Indiana, data center campus · Data Center Dynamics · retrieved July 6, 2026
  3. 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review