Data Center Registry
Iron Mountain White Oak Technology Park Campus
Henrico, Henrico County, Virginia · All 13 Iron Mountain sites
Iron Mountain White Oak Technology Park Campus is a proposed data center in Henrico, Virginia (Henrico County), operated by Iron Mountain. The public record puts it at announced November 2024, 200 MW planned, 66 acres, a reported $1 billion investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Iron Mountain
- Facility type
- Data center, AI use mixed
- Location
- Henrico, Henrico County, VA
- Coordinates
- 37.5560, -77.4270
- Power capacity
- 200 MW planned
- Land
- 66 acres
- Investment
- $1 billion
- Announced
- November 2024
- Utility
- Dominion Energy Virginia
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- November 2024ProposedIron Mountain CEO announced plans on Q3 2024 earnings call; company acquired 66-acre site at 6110 Technology Creek Drive from Henrico EDA for $8M. Four-building, 1 million+ sq ft campus planned. No build timeline shared. Source: Data Center Dynamics
Opposition and litigation at this site
Nothing on record as of July 23, 2026. No lawsuit, organized opposition, or contested hearing over Iron Mountain White Oak Technology Park Campus in Henrico, Henrico County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Located in White Oak Technology Park with established power and network infrastructure; neighbors Bank of America and QTS data centers
Notes on the record
6110 Technology Creek Drive, Henrico County (Richmond metro area). White Oak Technology Park has fiber connections and subsea cables to three continents. Henrico County passed stricter data center requirements June 2025, including 500-foot tree buffer near residential. investmentUsd is stated as 'more than $1 billion', treated as floor.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- DC Blox Henrico County Campus (withdrawn) · DC BLOX2 mi · Cancelled · 50 MW
- Flexential Richmond (RIC01/02) · Richmond · Flexential6 mi · Operating
- QTS White Oak Technology Park II (RIC5) · Sandston · QTS Data Centers10 mi · Permitted · Mixed reception
- QTS Richmond 1 DC1 (RIC1, White Oak Technology Park) · Sandston · QTS Data Centers11 mi · Operating
- Mountain Road Technology Park · Tract11 mi · Cancelled · 900 MW · Opposed
- Hunting Hawk Technology Park · Glen Allen · HHHunt13 mi · Cancelled · 900 MW · Opposed
- Chirisa Technology Park, Richmond (Chester) · Chester · PowerHouse Data Centers14 mi · Under construction · 120 MW · Mixed reception
- Iron Horse Data Center Campus · WestDulles Properties14 mi · Proposed
Questions people ask about this site
Is there opposition to the Iron Mountain White Oak Technology Park Campus in Henrico?
Nothing on record as of July 23, 2026. No lawsuit, organized opposition, or contested hearing over Iron Mountain White Oak Technology Park Campus in Henrico, Henrico County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Iron Mountain White Oak Technology Park Campus?
No lawsuit over Iron Mountain White Oak Technology Park Campus appears in the record we track as of July 23, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Iron Mountain White Oak Technology Park Campus use?
No water withdrawal figure for Iron Mountain White Oak Technology Park Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Iron Mountain White Oak Technology Park Campus, and how big is it?
Iron Mountain is the operator on record. We hold 13 sites for that company across the registry. Capacity on record is 200 MW. The site is recorded at 66 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Iron Mountain White Oak Technology Park Campus," updated July 23, 2026, https://suedatacenters.org/data-centers/iron-mountain-white-oak-henrico-va.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/iron-mountain-white-oak-henrico-va, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Iron Mountain acquires 66 acres outside Richmond for 200MW data center campus · Data Center Dynamics · retrieved July 6, 2026
- 2.Iron Mountain to build data center in Henrico's White Oak Technology Park · Henrico Citizen · retrieved July 6, 2026
- 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 4.VA DEQ air permit 53266-1, Iron Mountain Information Management, LLC (issued 2026-05-07) · Virginia Department of Environmental Quality · retrieved July 29, 2026
- 5.Submission provenance (not controlling source), Public Evidence record for permit 53266-1 · Public Evidence Project · retrieved July 30, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us