Vantage Pittsboro Campus is a permitted data center in Pittsboro, Indiana (Hendricks County), operated by Vantage Data Centers. The public record puts it at 400 MW planned, 626 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- Vantage Data Centers
- Facility type
- Data center
- Location
- Pittsboro, Hendricks County, IN
- Coordinates
- 39.8656, -86.4675 (approximate)
- Power capacity
- 400 MW planned
- Land
- 626 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- March 18, 2025PermittedPittsboro Town Council unanimously approved rezoning of the 626-acre site. Source: Inside INdiana Business
- February 2025ProposedRezoning request filed for a 618-acre site; Advisory Plan Commission voted 4-1 in favor. Source: Inside INdiana Business
Opposition and litigation at this site
Nothing on record as of September 1, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Pittsboro Campus in Pittsboro, Hendricks County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Colocation campus in the northeast corner of Pittsboro, north of I-74 and west of County Road 500 East, on land annexed into the town in late 2024. Roughly 285 of the 626 rezoned acres are planned for development, in three buildings reported at 256 MW, 96 MW and 48 MW. Third-party project trackers list the campus as later withdrawn; no press confirmation of a withdrawal was located as of 2026-09-01, so the last sourced status (rezoning approved) is recorded here.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Meta Lebanon (Project Domino) · Lebanon · Meta14 mi · Under construction · 1 GW · Supported
- Sabey Decatur Technology Park · Decatur Township · Sabey Data Centers15 mi · Permitted · 250 MW · In litigation
- Metrobloks Martindale-Brightwood Data Center · Indianapolis · Metrobloks19 mi · Permitted · 75 MW · In litigation
- Google Project Louie (Morgan County) · Monrovia · Google21 mi · Under construction · 390 MW · In litigation
- DC BLOX Warren Township Data Center · Warren Township · DC BLOX23 mi · Permitted · 78 MW · Contested
- Logix Reality Frankfort Data Center · Frankfort · Logix Reality LLC29 mi · Cancelled · Opposed
Questions people ask about this site
Is there opposition to the Vantage Pittsboro Campus in Pittsboro?
Nothing on record as of September 1, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Pittsboro Campus in Pittsboro, Hendricks County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Vantage Pittsboro Campus?
No lawsuit over Vantage Pittsboro Campus appears in the record we track as of September 1, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Vantage Pittsboro Campus use?
No water withdrawal figure for Vantage Pittsboro Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Vantage Pittsboro Campus, and how big is it?
Vantage Data Centers is the operator on record. We hold 20 sites for that company across the registry. Capacity on record is 400 MW. The site is recorded at 626 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Vantage Pittsboro Campus," updated September 1, 2026, https://suedatacenters.org/data-centers/vantage-pittsboro-in.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/vantage-pittsboro-in, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Data center developer eyeing 618-acre site in Hendricks County · Inside INdiana Business · retrieved September 1, 2026
- 2.Pittsboro officials OK rezoning of 626 acre-site for proposed data center campus · Inside INdiana Business · retrieved September 1, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us