Merrillville Technology Park is a proposed data center in Merrillville, Indiana (Lake County), operated by The Province Group. The public record puts it at a reported $500 million investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- The Province Group
- Facility type
- Data center
- Location
- Merrillville, Lake County, IN
- Coordinates
- 41.4600, -87.2900 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- $500 million
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- February 11, 2026ProposedReported as one of three early-stage Merrillville data center proposals. Source: Government Technology
Opposition and litigation at this site
Nothing on record as of September 1, 2026. No lawsuit, organized opposition, or contested hearing over Merrillville Technology Park in Merrillville, Lake County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
A 1 million sq ft campus near Colorado Street and Harms Road, close to the Hobart border, developed by Newport Beach, California-based Province Group at up to $500 million, with reported salaries up to $175,000. Distinct from the same developer's Bristol Innovation Park proposal in Elkhart County.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Karis Critical Deep River Campus · Merrillville · Karis Critical1 mi · Proposed
- Wylie Capital Broadway Data Center · Merrillville · Wylie Capital3 mi · Proposed
- AWS Hobart Campus · Hobart · Amazon Web Services4 mi · Under construction · 2.4 GW · Contested
- Project Shirley · Eagle Creek Township · Sentinel Data Centers10 mi · Proposed · 500 MW · Contested
- CoreWeave Digital Crossroads · Hammond · CoreWeave14 mi · Cancelled · 180 MW
- AWS Wheatfield Campus (Project Rise) · Wheatfield · Amazon Web Services22 mi · Permitted · Supported
- Google Michigan City Data Center · Michigan City · Google27 mi · Under construction
Questions people ask about this site
Is there opposition to the Merrillville Technology Park data center in Merrillville?
Nothing on record as of September 1, 2026. No lawsuit, organized opposition, or contested hearing over Merrillville Technology Park in Merrillville, Lake County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Merrillville Technology Park data center?
No lawsuit over Merrillville Technology Park appears in the record we track as of September 1, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Merrillville Technology Park use?
No water withdrawal figure for Merrillville Technology Park is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Merrillville Technology Park, and how big is it?
The Province Group is the operator on record. We hold 2 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Merrillville Technology Park," updated September 1, 2026, https://suedatacenters.org/data-centers/province-group-merrillville-technology-park-in.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/province-group-merrillville-technology-park-in, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.$2B+ in Data Center Projects Planned for Merrillville, Ind. · Government Technology · retrieved September 1, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us