Sue Data Centers

Data Center Registry

AAIM Data Centers, Blue Earth (Minnesota 1)

Blue Earth, Faribault County, Minnesota

OperatingNo reception on recordRecord updated August 8, 2026

AAIM Data Centers, Blue Earth (Minnesota 1) is an operating crypto mining site in Blue Earth, Minnesota (Faribault County), operated by AAIM Data Centers. The public record puts it at 15 MW operating.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
AAIM Data Centers
Facility type
Crypto mining
Location
Blue Earth, Faribault County, MN
Coordinates
43.6350, -94.0980 (approximate)
Power capacity
15 MW operating
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Nothing on record as of August 8, 2026. No lawsuit, organized opposition, or contested hearing over AAIM Data Centers, Blue Earth (Minnesota 1) in Blue Earth, Faribault County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

On Highway 169 in Blue Earth, MN (county seat of FARIBAULT County, note this is NOT 'Blue Earth County', which is a separate county to the east whose seat is Mankato; classic MN city/county name trap, verified via Wikipedia/Data Commons before writing this). AAIM's own site lists this as 'Minnesota 1', 15MW, in-service June 2025, described elsewhere (DCD, 2024) as an 'HPC/cryptomine' facility; AAIM's own copy says it serves 'high-performance computing, enterprise data, and crypto mining needs', classified facilityType=data_center/aiClassification=mixed_use rather than crypto_mining because AAIM operates it as multi-tenant colocation (landlord model) rather than mining for itself, unlike Revolve Labs. 10,000 sq ft facility. AAIM's CEO (Levesque) is also CTO of crypto-mining-hardware firm Hash House Tech, noted for context, not fact-changing.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the AAIM Data Centers, Blue Earth (Minnesota 1) data center in Blue Earth?

Nothing on record as of August 8, 2026. No lawsuit, organized opposition, or contested hearing over AAIM Data Centers, Blue Earth (Minnesota 1) in Blue Earth, Faribault County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the AAIM Data Centers, Blue Earth (Minnesota 1) data center?

No lawsuit over AAIM Data Centers, Blue Earth (Minnesota 1) appears in the record we track as of August 8, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does AAIM Data Centers, Blue Earth (Minnesota 1) use?

No water withdrawal figure for AAIM Data Centers, Blue Earth (Minnesota 1) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates AAIM Data Centers, Blue Earth (Minnesota 1), and how big is it?

AAIM Data Centers is the operator on record. Capacity on record is 15 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "AAIM Data Centers, Blue Earth (Minnesota 1)," updated August 8, 2026, https://suedatacenters.org/data-centers/aaim-data-centers-blue-earth-mn.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aaim-data-centers-blue-earth-mn, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Minnesota 1 - AAIM Data Centers · AAIM Data Centers (official) · retrieved August 8, 2026
  2. 2.AAIM to Launch Cutting-Edge Data Center in Blue Earth, Minnesota · AAIM Data Centers (official) · retrieved August 8, 2026 · original offline, archived copy from June 16, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us